Tempo hours with no person attached: capitalizing them without per-person rates

Radrly team5 min read

Also published on Atlassian Community

In this guide
  1. Why the person is missing
  2. The worked month
  3. Doing it natively
  4. The same month in CapRadar
  5. What to tell the auditor

On a site where Tempo is the time tracking provider, the month-end capitalization file often has a gap. Jira holds the hours, but on the Jira copy of each worklog the author is an app account, so the cost per person cannot be built from Jira alone.

CapRadar is a software capitalization and R&D time app for Jira Cloud from Radrly. This guide follows one worked month for one space on a Tempo site: the native way first, then how CapRadar handles the same hours, and finally what to tell the auditor about them. How capitalized cost is measured is a decision for you and your auditor; this is a walk through the data, not accounting advice.

Why the person is missing

Tempo's own help center explains it. On Jira Cloud, Tempo keeps worklogs in its own system and writes a copy to Jira with an app account as the author and "time tracking" as the comment. The Jira REST API returns that app account, and a JQL search by worklog author cannot identify the individual. The real author is available through the Tempo REST API. Tempo also recommends identifying its worklogs by the app account ID, because the display name of the app account can change.

You can confirm which provider your site uses in Settings > Work items > Time Tracking, in the Time tracking provider dropdown, as described in Configure time tracking. The same page notes that a third-party provider's data might be stored with the app developer.

The worked month

Space ATLAS, March. Eight people log time. Some of it arrives as native Jira worklogs with an author; the rest arrives through Tempo with no person on the Jira copy. Epics are already classified as CapEx or OpEx.

Hours in ATLAS, MarchCapExOpExRate usedCapEx cost
Worklogs with a person640260each person's rate41,600
Worklogs with no person380120space blended rate, 6825,840
Total1,02038067,440

The blended rate here is the loaded cost of the eight people in March (92,000) divided by their expected working hours (1,350), rounded to 68. That is one common way to set it. Whatever method you choose, write it down once and use it every month.

Doing it natively

  1. Pull the worklogs for the space and month with the Jira REST API. A search export gives one row per work item with total time spent, which loses the date of each worklog.
  2. Split the rows by author account ID: real people on one side, the Tempo app account on the other.
  3. Map each work item to its epic and to the CapEx or OpEx decision.
  4. In a spreadsheet, cost the attributed hours with each person's rate and the rest with the blended rate.

Honest limits. Jira stores no rates, so the rates live in the spreadsheet. Jira has no period lock: anyone with Edit own worklogs or Edit all worklogs (see Time tracking permissions), or Tempo writing on a user's behalf, can change March in May, and the spreadsheet will not know. If you want the person behind the Tempo hours, you need the Tempo REST API and a token with the right Tempo permissions, plus a script to join the two sources without counting any hour twice.

The same month in CapRadar

CapRadar reads the Jira copies of Tempo worklogs and reports those hours per work item, epic and space. On Standard they are costed with the space blended rate and labelled "no per-person attribution". Rates are effective-dated person, role, team and space rates imported by CSV. For people, CapRadar takes the person's rate, then the role rate, then the team rate, then the space blended rate. Tempo hours always use the space rate.

If the ATLAS space rate is missing, the Overview shows finance roles a note with a link to Rates. At close, missing rates and unclassified hours block the lock until they are fixed or a finance admin waives them with a reason, so the 500 Tempo hours cannot be locked at zero cost by accident. Approve and lock is part of Standard; a worklog changed later for a locked month becomes a post-lock adjustment in the next open period.

On screens that list people, these hours appear as "No person". The Organization report shows them as one "Unattributed (Tempo)" row, so the team total there can be lower than the Overview total, and the difference is the Tempo share.

If you want the person back, Advanced can import a Tempo report CSV (person, work item, date, hours) or a percentage CSV (person, epic, month, share). The result is labelled "imported attribution" and shown on Attribution, in R&D packs and in the method mix. Period totals and the close still use the worklogs, so the 500 hours are counted once.

What to tell the auditor

  • Source. 500 of 1,400 hours in ATLAS came from Tempo, where the Jira record carries an app account instead of a person. The Overview method mix shows the split.
  • Rate. Those hours were costed with the space blended rate, effective from a stated date, with the method written down: loaded cost divided by expected hours.
  • Completeness. The close could not lock with missing rates or unclassified hours unless a finance admin waived them with a written reason.
  • Stability. The locked month does not change; later edits appear as post-lock adjustments with their source period.
  • People. Per-person detail for those hours comes from an imported Tempo report (Advanced), shown separately from the worklog totals, or it is not claimed at all.

Quick answers

Why do Tempo worklogs in Jira have no person attached?

On Jira Cloud, Tempo keeps worklogs in its own system and writes a copy to Jira with an app account as the author and "time tracking" as the comment. The Jira REST API returns that app account and a JQL search by worklog author cannot identify the individual; the real author is available through the Tempo REST API.

How does CapRadar cost hours that arrive from Tempo?

CapRadar reads the Jira copies of Tempo worklogs and reports those hours per work item, epic and space. On Standard they are costed with the space blended rate and labelled "no per-person attribution". For people, CapRadar takes the person's rate, then the role rate, then the team rate, then the space blended rate; Tempo hours always use the space rate.

Can Tempo hours be locked at zero cost if the space rate is missing?

No. If the space rate is missing, the Overview shows finance roles a note with a link to Rates, and at close missing rates and unclassified hours block the lock until they are fixed or a finance admin waives them with a reason. Approve and lock is part of Standard, and a worklog changed later for a locked month becomes a post-lock adjustment in the next open period.

Can CapRadar show the person behind Tempo hours?

In Advanced, CapRadar can import a Tempo report CSV (person, work item, date, hours) or a percentage CSV (person, epic, month, share). The result is labelled "imported attribution" and shown on Attribution, in R&D packs and in the method mix, while period totals and the close still use the worklogs, so hours are counted once.